Skip to main content
  குறை நிவர்த்தி : + 044-4567 4567 (24x7)
TN Logo CM Photo
Minister Photo CMWSSB Logo

சென்னைப் பெருநகர் குடிநீர் வழங்கல் மற்றும் கழிவு நீரகற்று வாரியம்

.

New Water Connection for Commercial & Industries Dashboard for the Month of February, 2024

Updated as on – 18-06-2024 06:00 PM

New Water connection for Commercial / Industrial
Particulars Details
Time Limit prescribed 15 Days
Total Number of application received 45
Total Number of applications approved 80
click here
Average time taken 21 Days
Median time taken 10 Days
Minimum time taken 01 Day
Maximum time taken 160 Days
Average fee collected by CMWSSB for Connection Rs.38,173/-

Back