New Water Connection for Commercial & Industries Dashboard for the Month of January, 2024

Updated as on – 18-06-2024 06:00 PM

New Water connection for Commercial / Industrial
Particulars Details
Time Limit prescribed 15 Days
Total Number of application received 31
Total Number of applications approved 49
click here
Average time taken 28 Days
Median time taken 10 Days
Minimum time taken 02 Day
Maximum time taken 134 Days
Average fee collected by CMWSSB for Connection Rs.44,155/-